PROJECT AUTHORIZATION |
PACKET ID: PMT-LMMD |
CONTRACT ID |
EMARS PROGRAM CODE |
AUTHORIZATION NO: |
|
1529101D |
15291 |
0 |
It is hereby ordered that the project herein described be undertaken and accomplished within the funding level authorized. |
PROJECT ID |
PROJECT ID NUMBER |
FEDERAL PROJECT NUMBER |
6 YR PLAN ITEM NUMBER |
6 YR PLAN ITEM PARENT NUMBER |
|
034 000 4 013-015 |
NHPP 4181032
|
07-00438 |
|
PROJECT TYPE |
PROJECT LENGTH |
NUMBER OF BRIDGES |
SYSTEMS |
RECONST W/WIDER LNS |
MI |
|
|
PROJECT PHASE
&
RESPONSIBILITY |
PLANNING |
DESIGN |
RIGHT OF WAY |
UTILITIES |
|
|
|
|
CONSTRUCTION |
TITLE DEEDED TO: |
MAINTENANCE |
OTHER |
|
|
|
|
FUNDING & TIME
ACCOUNTABILITY |
PARTICIPATING AGENCIES |
FEDERAL |
FHWA |
STATE |
KYTC |
LOCAL |
|
OTHER |
|
REQUESTED FUNDS FOR THIS AUTHORIZATION
ITEM NUMBER |
PHASE |
FUND |
PROGRAM |
FEDERAL FISCAL YEAR |
STATE FISCAL YEAR
|
FEDERAL APPR
CODE |
CURRENT FUNDING REQUEST |
7-438 |
D |
1200 |
FD52 |
2022 |
2022 |
Y001 |
$1,600,000.00 |
7-438 |
D |
1100 |
FD52 |
2022 |
2022 |
|
$400,000.00 |
CURRENT FUNDING REQUEST TOTAL: $2,000,000.00 |
AUTHORIZATION SUMMARY FOR THIS 10-1 SERIES |
PHASE |
TOTAL AUTHORIZATION TO DATE (INCL. CURRENT REQUEST) |
PLANNING |
$0.00 |
DESIGN |
$2,000,000.00 |
UTILITIES |
$0.00 |
R/W |
$0.00 |
CONSTRUCTION |
$0.00 |
NON-HIGHWAYS |
$0.00 |
|
Total: $2,000,000.00 |
THIS AUTHORIZATION PROVIDES $2,000,000 FEDERAL NH FUNDS FOR THE DESIGN PHASE OF THE PROJECT WITH STATE FUND MATCH. |
|
Project Approval Recommended By:
James Ballinger 7/11/2022 |
Signed and Approved by:
Jim Gray 7/12/2022 |
ITEM NO. |
COUNTY |
DIST |
FACILITY NAME
|
ROUTE |
LENGTH |
07-00438.00 |
FAYETTE
|
7 |
E NEW CIRCLE RD |
KY 4 |
MI |
REDUCE CONGESTION ON KY-4 (NEW CIRCLE RD) FROM TRADE CENTER DR TO WOODHILL DR. |